Electrical Installation (HV/EHV) and Diesel Generator Registration/Noc for Increase in Load Dashboard For Citizen

Application NameTotal CountPendingApprovedRejectSend BackAverage time taken to obtain registrationMedian time taken to obtain registrationMinimum Time taken to Obtain RegistrationMaximum Time taken to obtain registrationAverage Cost
Drawing Approval Under HV/EHV 8875 11 8043 200 615 02.21 7 0 71 143533.35
Work completion Under HV/EHV 8091 8 7587 160 325 04.17 7 0 70 117686.79
Noc for Increase in Load 0 0 0 0 0 0 0 0 0 0

*Last updated on 03/04/2026 ( The dashboard is updated on daily basis)